Project Description

Green Roof Project, St Pancras Way, London

Mead Construction needed to install green roofs over three small rooftops on the same block in St Pancras Way, London. But there were access issues at the building which meant that installing a traditional roll-out ‘blanket’ green roof would be problematic. So our modular M-Tray® system was recommended (through CMOstores.com):

This project involved the refurb of an existing building for conversion into flats right next to the Regent Canal. The design, which included a new extension, called for a number of green roofs.

The contractor had serious access issues on site not only for delivery but also in order to get the materials to site as it was the roof of the 4th floor and there was no crane or hoist. What they did have was a pully hoist which allowed them to lift one tray at a time.

The work took 2 days including lifting the trays onto the roof one at a time.

If you are considering installing a green roof give us a call on 0208 916 2222 to talk to our knowledgeable team or drop us a line using the enquiry form or live chat facility in the bottom right hand corner of your screen.